Sign in
|
Register
|
Mobile
Home
Browse
About us
Help/FAQ
Advanced search
Home
>
Browse
>
Project Management in Construction, Sixth Edition
CITATION
Levy, Sidney
.
Project Management in Construction, Sixth Edition
.
US
: McGraw-Hill Professional, 2011.
Add to Favorites
Email to a Friend
Download Citation
Project Management in Construction, Sixth Edition
Authors:
Sidney Levy
Published:
August 2011
eISBN:
9780071753098 0071753095
|
ISBN:
9780071753104
Open eBook
Book Description
Table of Contents
Contents
Preface
Chapter 1. An Introduction to the Construction Industry
Critical Issues Facing Contractors in This New Millennium
How our industry is perceived
Information technology
Human resources—the changing workforce
Undocumented immigrant problem
Productivity
Quality control
Project delivery systems
The organization
Construction technology
Safety
The changing marketplace
Chapter 2. The Start of the Construction Process
The Letter of Intent
Defining costs in the letter of intent
Subcontractor commitments via the letter of intent
The letter of intent termination clause
Prevalent Types of Construction Contracts
Cost of the work plus a fee
The stipulated or lump-sum contract
The cost-plus-a-fee with a GMP contract
Construction manager contracts
Program manager
The joint venture agreement
Turnkey contracts
Build-operate-transfer
Contracts with government agencies
Chapter 3. The General Conditions to the Construction Contract
AIA A201—General Conditions of the Contract for Construction
Article 1: General provisions
Article 2: Owner
Article 3: Contractor
Article 4: The architect
Article 5: Subcontractors
Article 6: Construction by owner or by separate contractors
Article 7: Changes in the work
Article 8: Time
Article 9: Payments and completion
Article 10: Protection of persons and property
Article 11: Insurance and bonds
Article 12: Uncovering and correction of work
Article 13: Miscellaneous provisions
Article 14: Termination or suspension of the contract
Article 15: Claims and disputes
AIA Document A232—General Conditions for the Construction Manager Contract
A Word to the Wise
Chapter 4. ConsensusDOCS, Integrated Project Delivery, and Lean Construction Contracts
The American Institute of Architects—AIA Integrated Delivery Project
C191-2009, Standard Form Multi-Party Agreement for Integrated Project Delivery
C195-2008, Standard Form Single Purpose Entity Agreement for Integrated Project Delivery
Exploring the Limited Liability Company Concept
ConsensusDOCS
ConsensusDOCS 200, Standard Agreement and General Conditions Between Owner and Contractor (Where the Contract Price Is a Lump Sum)
ConsensusDOCS 200.1, Potentially Time and Price Impacted Materials
ConsensusDOCS 200.2, Electronic Protocol Addendum
ConsensusDOCS 300, Standard Form of Tri-Party Agreement for Collaborative Delivery
ConsensusDOCS 400, Standard Design-Build Agreement and General Conditions Between Owner and Design-Builder (Where the Basis of Payment Is the Cost of the Work with a GMP)
ConsensusDOCS 500, Standard Agreement and General Conditions Between Owner and Construction Manager (Where the Basis of Payment Is a Guaranteed Maximum Price with an Option for Pre-Construction Services)
ConsensusDOCS 750, Standard Form of Agreement Between Contractor and Subcontractor
Lean Construction
Section 3, Relationship of the Parties
Section 4, Formation and Functioning of the Core Group
Section 5, Collaboration and Integrated Preconstruction Services
Section 6, Project Planning and Scheduling
Section 10, Development of Design Documents
Section 11, Value Engineering, Constructability, and Work Structuring
Section 12, Guaranteed Maximum Price Proposal and Contract Time
Section 13, Financial Responsibilities and Project Contingencies
Section 15, Construction Phase Operations
Section 27, Quality of Work and Services
These New Documents Raise Insurance, Legal, and Claims Concerns
The Legal Concerns
Chapter 5. Bonds and Insurance
This Risky Business
Bonds for Projects in Government Projects—The Miller Act
Why Contractors Fail
Bonds and the Bonding Process
The terminology of bonds
Ten things you should know about surety bonding
The letter of credit
The bonding process
Prequalifying for a bond
Insurance
Builder’s risk
Workers’ compensation insurance
Subcontractor default insurance
Subguard®-Default Insurance for Subcontractors
Controlled insurance programs
Insurance terms
Are New Insurance Requirements on the Horizon?
Chapter 6. Organizing the Project Team
Organizing the Job in the Office
Changing CSI specification division numbering
Addenda and bulletins
Project files
Organizing the Estimate
Investigating allowance and bid alternates
Alternates
Shop drawings and the shop drawing log
Informational copies
The RFI log
Job scheduling
The critical path method (CPM)
Activity duration times
The importance of float and who owns it
The project meeting minutes
Other forms to consider when getting organized
Lien waivers—for progress and final payment
Organizing in the Field
Shop Drawing Organization
The Future of Project Organization
Chapter 7. Successful Project Completion Demands a Successful Start
Starting Off on the Right Foot
Controlling the Project Start
Review of the Contract with the Owner
Review of the Project Specifications
Specific items to look for when reviewing the specifications
Record Drawings
Inspections and Test Reports (Other Than Those Required by Local Officials)
Operations and Maintenance Manuals
Commissioning and TAB
TAB—A Procedure That Requires Special Attention
Commissioning
The Punch List
Is it a punch list or a warranty item?
Attic stock, special tools, and spare parts
Material safety data sheets
Preparing for that First Project Meeting with the Subcontractors
That Dangerous End-of-Project Syndrome
A Building Systems Commissioning Checklist
Chapter 8. Estimating
The 2010 Edition of CSI’s MasterFormat®
Acquiring a Database
The purchased database
Acquiring the in-house database
The weekly field labor report
Combining cost codes and daily reports to produce the database
Analyzing Unit Costs
Displaying unit costs
Monitoring the reporting of costs
When disparities in costs appear
Bundling to create a unit cost
Conceptual Estimating
The various stages of the process
The Postconstruction Project Review
Mining Completed Projects to Enhance the Database
The Project Parameter Cost Model Form
The preparation of a project cost model data sheet
Sources of Conceptual Estimating Data
Cost index data
Order-of-Magnitude Estimating
Order-of-magnitude issues to consider
Special Requirements Associated with Office Building Estimating
Core and shell
The Tenant Work Letter
The Developer’s Responsibility
Subcontractor Responsibilities as They Relate to Tenant Fit-Ups
Chapter 9. Buying Out the Job
Reread the Contract with the Owner
Awarding Subcontracts
The subcontract interview form
The Bid Summary Sheet
Unit Prices
Other items to consider during the solicitation of prices
Combining Work to Best Advantage
Subcontract or Do It Ourselves?
The “we can do it cheaper” syndrome
Key Questions to Ask Subcontractors during Negotiations
Pitfalls to Avoid in Mechanical and Electrical Contract Negotiations
Who Is the Contractor?
Issues to Be Addressed
Temporary light and temporary power
Installation of underground utilities
Designing to local utility standards
Warranties and Guarantees
Spare Parts, Special Tools, and “Attic” Stock
Job Cleaning and the Contract
Communicating the Terms and Conditions of the Subcontract Agreement
Importance of lien waiver requirements in the subcontract agreement
Purchase Orders
Ordering when exact quantities are not known
Price protection and the purchase order
Pitfalls to Avoid When Issuing Subcontracts and Purchase Orders
Do Your Subcontract Agreements Include These Key Provisions?
Chapter 10. The Change Orders
A Cardinal Rule
Starting off on the right foot
Other questions to consider as potential costs in addition to those above
Reviewing the Important Contents of a Change-Order Request
Time and material work
The verbal authorization to proceed
What Constitutes “Cost”
Watch Those Hourly Payroll Costs
Completion Time and the Change Order
Consequential damages
Will contract time remain the same, be reduced, or be extended?
Small-tool costs
What costs other than bricks and mortar should be considered?
What overhead and profit fees can be included in change-order work?
When credits and charges both apply
The construction change directive—the CCD
Be alert to other contract provisions relating to change-order work
Public Works and the Change-Order Process
Will this change affect productivity or overtime?
Roadblocks to Acceptance of Change Orders
The owner’s perspective
The contractor’s perspective
The architect and engineer’s perspective
Liquidated Damages and the Change-Order Process
A typical liquidated damages clause
Change Orders Reflecting Costs due to Job Delays
Excusable delays
Concurrent delays
Compensable delays
Documenting compensable delays
The cost impact associated with delays, interruptions, suspension of work
When submitting the change order
Pitfalls to Avoid when Preparing Change Orders
The Change-Order Cost Checklist
Effective Change-Order Control
Chapter 11. Quality Control and Quality Assurance
Quality Begins with Quality Design
Strategies for Change
Total Quality Management
Benchmarking
The International Standards Organization
The Six Sigma Approach to Quality
From Theory to Practice
Quality control by observation
Quality starts with a thorough review of the contract documents
Quality Control and the Specifications
The F factor
Using trade organizations to learn about quality standards
The Preconstruction Conference—QC and QA
Sample panels and mock-ups
The punch list and QC/QA
Developing a Company QC/QA Program
The inspection checklist method
Chapter 12. Project Documentation
The Documentation Process
Documentation to the Owner
The unique provisions of a GMP contract with respect to documentation
Documentation to an owner from the construction manager
Documentation to the Architect and Engineer
Shop drawing submittals, review, returns, and logs
Requests for Clarification and Requests for Information
Field Conditions Documentation
The affect on “as-builts”
The Coordination Process
Other Important Documents
Cost proposal or cost estimate requests
Conditions that impact completion time
Documentation of close-out requirements
Documentation to the Subcontractors
Is the scope of the work fully understood by all?
Avoiding problems related to subcontractor misunderstandings
Linking the subcontract agreement with the owner’s contract
Subcontractor performance—the major concern
Danger signs and how to interpret them
That low subcontract bid—are problems waiting to surface?
Documentation When Major Drawing Revisions Are Made
What to do with all of those 8½ × 11s
What Impact Have These Major Revisions Had on Productivity?
Documentation Required When Contracting with Public Agencies
The Davis-Bacon Act
Complying with other government requirements
Project Documentation from the Field
The superintendent’s record of daily activities
Photographs: important documentary components
Chapter 13. Claims, Disputes, Arbitration, and Mediation
What Triggers Claims and Disputes?
The Bid Proposal Process and the Potential for Disputes
Do late bids count?
Other Potentials for Disputes
Oral contracts
Disputes regarding contract interpretation
Subsurface, changed, and differing conditions
What is different about “differing conditions”?
Differing Site Conditions (DSC)
Using geotechnical disclaimers to advantage
The court and differing site conditions
Shift Work and Its Impact on Productivity
Differing or changed conditions
Changed Conditions
Be wary of subcontractor input
A word about lost productivity
The courts and lost productivity issues
Claims against professionals
Acceleration: what it is and how it is used
Arbitration and Mediation
Mediation
The arbitration process
In Summation
Chapter 14. Safety in Construction
The Occupational Safety and Health Act (OSHA)
Factors Responsible for Declining Accident Rates
Safety Pays—in More Ways Than One
The positive effects of a good safety record
Workers’ compensation insurance
Developing the Company Safety Program
The statement of company policy
The safety director/safety coordinator
A hazard communication program
Chapter 15. Design-Build
What Is Design-Build?
Why has design-build garnered so much attention recently?
Developing a Design-Build Capability
Creating in-house design capability
The joint venture
The limited liability corporation—the LLC
An architect-or contractor-led design-build team?
Developing a Design-Build Program
Developing design-build proposals
The two-phase design-build proposal
The use of stipends
Another approach
How Owners Select Design-Builders
The selection process
Using Contract Incentives
Several forms of design-build contracts
The teaming agreement
Contract Provisions Unique to the Design-Build Process
Special provisions of design-build contracts
Contract provisions relating to defining the owner’s program
The role of the subcontractor in the design-build process
Design-Build in the Public Sector
Federal Design-Build Contracting
U.S. Department of Transportation (USDOT) Design-Build Effectiveness Study of January 2006
Evaluation of the phase two proposers
Chapter 16. Sustainability and Green Buildings
The Impact of Construction on the Environment
What Do We Mean by Sustainability?
What are some of these eco-friendly materials?
Whole-building design
Green buildings in the private sector
Some Design-Build/Sustainable Building Guidelines
Are green buildings more expensive than conventional construction?
Projected savings
Other revealing but not so apparent benefits of green buildings
The Greening of Existing Buildings
JohnsonDiversey Continues to Innovate
Chapter 17. Interoperability and Building Information Modeling (BIM)
Looking at the Last Several Decades
Contractors Slow to Embrace Technology
Interoperabilty—what is it and why is it so important?
The steel industry becomes a leader
What Is Building Information Modeling All About?
Coordination and interference issues addressed
Index